A Data Center Lawyer Warned One Palm Beach County Employee She Could Be Sued Personally. Ten Days Later the County Approved the Expansion.

0
65

Illustrative image of the Project Tango site area north of Southern Boulevard at 20-Mile Bend, west of Arden.

A letter sent to Palm Beach County on Sept. 28 warned that the county could face “catastrophic financial liability” over its review of a proposed AI hyperscale data center, and singled out the county’s zoning director for potential personal liability.

Ten days later, Zoning Director Wendy Hernandez signed an administrative decision allowing the data center space on the site to grow from 200,000 square feet to nearly 700,000 square feet, subject to conditions. The decision did not authorize construction. It did, however, allow the expansion without a public hearing or a commission vote.

The timing raises a consequential question for western Palm Beach County: how did staff approve an additional 500,000 square feet of data center uses after commissioners had voted against a larger expansion, and while the county’s data-center moratorium was in effect?

The documents show pressure on county staff. They do not, on their own, establish that the letter caused the Oct. 7 decision. The legal and procedural context is more complicated: PBA Holdings was entitled to a decision on its application under the rules then in force, and county staff faced potential legal exposure if it handled that application improperly.

A warning to the county, and its zoning director

In a Sept. 28 letter to county officials, Tampa attorney Ethan Loeb, representing longtime property owner PBA Holdings, formerly Palm Beach Aggregates, said the company was prepared to sue if staff imposed requirements not contained in the county’s Unified Land Development Code, or ULDC.

The letter said failure to follow the zoning code “exposes the county to significant and potentially catastrophic financial liability.” Loeb added that damages could be so large the county might be unable to pay without “a bond or other extraordinary funding mechanism.” He also wrote: “Moreover, Ms. Hernandez must understand the significant personal liability that she is creating for herself.”

Loeb said PBA Holdings was “fully prepared to sue the county” unless Hernandez and other departments stopped imposing requirements that the company believed were not in the code. The letter cited potential claims under Florida’s Bert J. Harris Private Property Rights Protection Act. Read the Sept. 28 letter.

The state law gives property owners a route to seek compensation when government action inordinately burdens their property rights. It does not mean every zoning dispute produces damages, or that PBA’s threatened claim would succeed. But the possibility of a costly claim formed part of the legal risk county staff had to weigh.

Illustrative image of a county zoning office interior

Illustrative image of a county zoning office. Zoning Director Wendy Hernandez signed the Oct. 7 administrative decision.

What the administrative decision changed

The 202-acre Project Tango site is north of Southern Boulevard at 20-Mile Bend, west of Arden. A Florida Power & Light natural-gas plant sits across from it. The Oct. 7 decision allowed data center space to increase to nearly 700,000 square feet from 200,000 square feet, according to Stet News’ review of the approval.

The decision came with conditions, some of which PBA disputed. Loeb objected to staff requests for the facility’s megawatt capacity, a decommissioning “business model,” confirmation that the end user was not a foreign entity under a statute regulating public utilities, and an 850-foot building setback. He argued the setback did not appear in the ULDC, called one staff comment “nonsensical” and referred to a possible “shift in the apparent political winds.”

In other words, the dispute was not simply whether the county could ask questions about a large data center. It was whether staff could require particular information or impose particular conditions under the zoning rules governing this application. The county’s Nov. 18 presentation to commissioners set out the staff decision and review.

Commission votes, legal risk and a divided board

The administrative approval followed a different, larger fight. On July 15, commissioners voted 5-1 to reject PBA’s proposed expansion of the overall project, citing incompatibility with surrounding uses. The proposal under that review would have increased the project to 3.6 million square feet from 2.02 million.

Opposition had intensified after the project’s hyperscale data-center character became clear in December 2025. Earlier plan changes had drawn little or no opposition, including the addition of 64 acres in January 2024.

At the Nov. 18 commission meeting, three commissioners questioned how staff could approve an additional 500,000 square feet without bringing the matter back to the board. No one raised the Sept. 28 letter during that discussion, according to Stet News.

Commissioners Katherine Waldron, Marci Woodward and Maria Sachs objected to the process. Waldron, who represents the area, later told Stet News the letter was “a personal threat toward a county employee,” adding that, in her view, it “corrupts the entire process” and the decision should be overturned.

Joel Flores, Maria Marino and Bobby Powell argued staff had to apply existing county rules and prior commission decisions. Flores warned that the county could be sued and lose if it did not follow the required process. County Administrator Joe Abruzzo backed staff’s decision, saying a midstream change in regulations could expose the county to a lawsuit “in the billions and billions of dollars.” He also characterized the situation as applicants “working the system.”

Woodward pointed back to the July vote, saying commissioners had discussed power, water, sound and other impacts, yet the staff decision made that debate feel irrelevant. The seventh commissioner, newly elected Erica Whitfield, did not take a position, Stet News reported.

At a July hearing, PBA estimated that the property with a larger data center and more warehouses would be worth $34 billion. That figure is the applicant’s estimate, not an independently established valuation.

Illustrative image of a natural-gas power plant

Illustrative image of a natural-gas plant. A Florida Power & Light natural-gas plant sits across from the proposed data-center site.

A second legal challenge to the process

The county approved a “zoning in progress” notice on July 7, putting applicants on notice that new data-center applications would no longer be accepted. In September, it enacted a moratorium on data-center applications. County attorneys have warned that the moratorium is good for only a year.

Arden community attorney John Eubanks argues the county should have rejected PBA’s application because the company did not give the required five days’ notice before seeking an extension of the county’s 120-day review deadline. In a Nov. 18 letter, Eubanks said the extension should not have been granted and that the application was “null and void.” If accepted, his argument could mean PBA was blocked by the moratorium. Read Eubanks’ Nov. 18 letter.

Eubanks has also challenged a separate proposal by WPB Logistics Owner to convert 1.2 million square feet of warehouse use into 1.1 million square feet of data-center use. He argues the application came too late, pointing to a July 14 resubmission after the July 7 notice. County officials say the application was first filed June 16 and was deemed insufficient on July 1 because it lacked a document. Eubanks’ earlier letter lays out his challenge to the WPB Logistics filing. Read the letter.

The next decision, and the one-year clock

PBA Holdings sued the county on Oct. 9 under Florida’s Land Use and Environmental Dispute Resolution Act, or FLUEDRA, after the parties could not agree on a magistrate to review the July denial. The lawsuit ended Nov. 19 when the county and PBA agreed on retired Palm Beach Circuit Judge James Martz, County Attorney David Ottey told Stet News. The sides are aiming for a public hearing on Dec. 7.

Martz will consider whether PBA is entitled to expand the project to 3.6 million square feet from 2.02 million. His recommendation will be nonbinding and will go to the County Commission, which can accept or reject it. PBA could sue if it disagrees with the commission’s decision.

Commissioners have also created a seven-person technical advisory committee to help develop new data-center rules. Three appointees named in Stet News’ reporting are Gary Brown, appointed by Sachs; Seacoast Utility Authority Executive Director Rim Bishop, appointed by Marino; and Arden resident and engineer Santiago Lattanzio, appointed by Waldron.

The board also approved hiring Vanasse Hangen Brustlin Inc., or VHB, for up to $225,000 to help rewrite the zoning code. Chief Deputy County Administrator Patrick Rutter said “time is of the essence,” with the county about 10 months into the period for producing rules and completing the public process before the moratorium expires.

The central issue is larger than whether Project Tango ultimately gets built. It is whether a major increase in permitted data-center space can be approved at staff level, without a public hearing, after commissioners voted against a larger expansion. The Sept. 28 letter is part of that record of pressure, but it does not settle whether the Oct. 7 decision was legally required, properly issued or subject to challenge.

The Dec. 7 hearing, the commission’s response to Martz’s recommendation, Eubanks’ deadline argument and the county’s progress on new regulations will help determine what comes next.